Fixed
Surface of the Ford has seriously eroded.
Reported via mobile in the Carriageway surface problem category anonymously at 16:32, Wednesday 6 March 2024
Sent to Shropshire Council less than a minute later. Council ref: 14140196.
There is serious surface resin within and when entering and exiting the Ford causing vehicle damage. This has been like this for several months but is worsening.
Updates
-
Thank you for contacting us. This note is to confirm that we have received your report and we'll be in touch with an update as soon as possible.
Posted by Shropshire Council at 16:32, Wednesday 6 March 2024
-
We have now arranged for the required work to take place to resolve the issue you reported to us.
We will update you when the work has been completed.
State changed to: Action scheduled
Posted by Shropshire Council at 10:45, Wednesday 20 March 2024
-
Can you say when this damage will be repaired. It is getting worse every day
Posted anonymously at 09:20, Tuesday 2 April 2024
-
This work still has not been resolved. Can you say when it will be done? The water level in the ford is the lowest it is going to get
Posted anonymously at 07:08, Monday 1 July 2024
-
This work still has not been resolved. Can you say when it will be done? The water level in the ford is the lowest it is going to get
Posted anonymously at 07:09, Monday 1 July 2024
-
We attended the issue you reported and are unable to start work due to an obstruction preventing sufficient access. We are unable to give you a timescale to completion. We will update you when action has been taken.
Posted by Shropshire Council at 09:02, Monday 29 July 2024
-
We have now arranged for the required work to take place to resolve the issue you reported to us.
We will update you when the work has been completed.
Posted by Shropshire Council at 10:22, Monday 29 July 2024
-
Please can you say what the obstruction was please? Unless it water running through the ford i cant imagine what the obstruction was. As weeks go by it will become increasingly difficult to repair as the water levels will rise. I look forward to your reply
Posted anonymously at 17:52, Monday 29 July 2024
-
We attended the issue you reported and are unable to start work due to an obstruction preventing sufficient access. We are unable to give you a timescale to completion. We will update you when action has been taken.
Posted by Shropshire Council at 07:42, Wednesday 7 August 2024
-
We have now arranged for the required work to take place to resolve the issue you reported to us.
We will update you when the work has been completed.
Posted by Shropshire Council at 08:54, Tuesday 13 August 2024
-
We're pleased to advise you that this work has now been completed.
State changed to: Fixed
Posted by Shropshire Council at 15:07, Thursday 5 September 2024