Action scheduled
Several Drains Blocked
Reported via desktop in the Drain blocked category anonymously at 10:55, Tuesday 27 February 2024
Sent to Shropshire Council less than a minute later. Council ref: 14139166.
Several drains along this road are blocked causing flooding, mud being churned up by farm vehicles is not helping, drains have been blocked for some time
Updates
-
Thank you for contacting us. This note is to confirm that we have received your report and we'll be in touch with an update as soon as possible.
Posted by Shropshire Council at 10:55, Tuesday 27 February 2024
-
We have looked into this issue and can advise that the work required will be completed in our programme of upcoming routine maintenance.
State changed to: Closed
Posted by Shropshire Council at 11:10, Monday 4 March 2024
-
Customer rang back to say the road is under approx. 6 - 7 inches of water and the work needed to sort this out is not routine. He wants to be notified of the date the contractors will be coming out to carry out the work to sort the issue out. He will be sending photographs in to show the extent of the issue.
Posted anonymously at 10:55, Friday 5 April 2024
-
The issue you reported has been assessed and the necessary work will be included in our programme of upcoming maintenance.
Our priority is to be effective at responding to the most serious problems so at this time we are unable to provide an exact timescale.
In the meantime until these works can be undertaken, we will continue to undertake routine inspections, whereby notifiable issues are recorded and scheduled for action.
State changed to: Action scheduled
Posted by Shropshire Council at 12:57, Wednesday 10 April 2024
-
We're pleased to advise you that this work has now been completed.
State changed to: Fixed
Posted by Shropshire Council at 12:47, Friday 12 April 2024
-
Drains are still blocked , this is causing flooding. Some drains are buried and will ned a resident to show where these are located .
State changed to: Open
Posted anonymously at 09:51, Wednesday 17 April 2024
-
Customer has called back in to chase this up as the work has not been completed yet. It needs to be properly completed soon as the drains have been blocked for over a year, and last winter was particularly bad for the residents. He said that he has marked out a number of the drains for the team to clean out and wants it to be done soon, or he will take this higher as it is not acceptable to him to say the work is done when it hasn't been.
Posted anonymously at 13:17, Thursday 8 August 2024
-
State changed to: Fixed
Updated by Shropshire Council at 11:49, Monday 12 August 2024
-
Customer called back to follow up on the email he received stating the work has been completed. He is angry that it has been closed off as completed, stating that none of the drains have been touched and sent in some more photographs to show this. He said that this is completely unacceptable and will also be following up with an email to Andy Wilde about this as well
Posted anonymously at 11:17, Wednesday 14 August 2024
-
We have now arranged for the required work to take place to resolve the issue you reported to us.
We will update you when the work has been completed.
State changed to: Action scheduled
Posted by Shropshire Council at 01:19, Thursday 15 August 2024
Only the original reporter may leave updates. If you made the original report please log in to leave an update.